- November 2024: Groundbreaking
-
June 2025: Slab on grade poured. Steel installation is complete. Second level decking is near complete. Roof decking is progressing. Mockup structure construction is nearly complete. CRA Trustees approved use of funds to cover cost of utility underground, joint users and restoration. Council approved ILA with PSTA for their reimbursement to the City. Council approved Underground Conversion and Utility Relocation Agreements and payment to Duke Energy.
May 2026: Major Tasks Completed
- Terrazzo floor tile
- Carpet tile and luxury vinyl plank floor tile installation complete,
- Final coat of paint throughout
- Wood accent band installed exterior of training room and chamber
- Storefronts installed
- Built-in reception desks installed
- Chamber dais complete
- Interior light
- Fixture installation complete
- Plug and switch
- Fire alarm system operational
- Fire sprinkler system
- Exterior architectural metal tile
Upcoming Tasks
- Complete walk off mat floor
- Complete ceiling tile installation
- Complete solar array installation
- Complete the installation of west side park and associated landscaping
- Commission building systems
- CMAR coordinating with CSX to complete parallel parking along S East Ave
- Begin coordination for furnishings installation and prepare department moves
Duke Undergrounding
Undergrounding is complete on Myrtle Ave. up to PSTA facility. Duke needs to complete work around PSTA.
-
June 2026: Major Tasks Completed
-
Building is substantially complete
-
Architect and Owner punch list walk through were performed for the interior.
Upcoming Tasks
- Site work continues along the south side park and associated irrigation
- Landscaping and site work along S. Myrtle Ave
- Commissioning of building systems
- Parking
- Furniture move-in
- Beginning the coordination for furnishings installation and preparation of department moves