Osceola Parking Garage, Pierce Street & Osceola Avenue

  • Project typeParking Garage
  • Project cost$25.7 million
  • Project scheduleConstruction Start: November 2025. Estimated construction completion: January 2027
  • Contractor nameCreative Contractors Inc.
Osceola Garage Rendering

Project Background

The project includes construction of a public parking garage at the corner of Pierce Street and Osceola Avenue, with 397 parking spaces. The land was acquired from Peace Memorial Church and certain stipulations were agreed to in the purchase agreement.

In addition to public parking, the finished garage will provide guaranteed parking to Peace Memorial Church during specified days associated with their church services. The building will also require a commercial wrap on the first floor to meet downtown development guidelines. 

Project Task Update

Major tasks completed:

  • 47 of 59 drilled shafts installed.

Upcoming tasks:

  • Continuation of drilled shaft installation.
  • Continuation of grade beams

Strategic Priorities

  • 1.2: Maintain public mobility systems through systematic management efforts.
  • 1.5: Embrace a culture of innovation that drives continuous improvement and serves all our customers.
  • 2.1: Strengthen public-private initiatives that attract, develop, and retain diversified business sectors.
  • 2.3: Promote Clearwater as a premiere destination for entertainment, cultural experiences, and tourism.
  • 3.2: Preserve community livability through responsible development standards and targeted revitalization.
  • 4.4: Develop accessible and active transportation networks that enhance pedestrian safety and reduce greenhouse gas emissions.

Updated Project Photos

Photograph showing the Placement of Caissons on a Clearwater construction site

Placement of Caissons 

Photo of Formed Grade Beams on a Clearwater construction site

Formed Grade Beans


Location

Pierce Street & Osceola Avenue,  33755  View Map